Cloud Outages and Force Majeure: What Counts as a Breach of Availability

· 10 min read

A founder scratches his head with a sheepish grin at a laptop outage error while an older CTO in glasses smiles and points at the contract.

In a single week of November 2026, several critical systems failed within days of each other. A major cloud service provider outage caused business disruption across North America lasting nearly 24 hours, during which communications were unreliable or unavailable.[1]

The cause traced to a defect introduced in a July 2026 update to networking gateway servers, which became unresponsive under specific load conditions due to lock contention. On November 13, the Federal Aviation Administration ("FAA") experienced a technical problem that resulted in a nationwide ground stop.[2] According to the FAA, its legacy equipment became unstable as a result of excessive data flooding. Only a few days later, a software bug in a major bank's on-premise hardware systems caused another outage.

Canadian organizations were among those affected. These events highlight how dependence on a small number of technology providers can turn a single failure into disruption across businesses and essential services.

In the European financial sector, the Digital Operational Resilience Act (DORA) requires financial institutions and their critical technology providers to prepare for disruptions in advance, through oversight, vulnerability management, and tested business continuity planning.[3]

In the absence of a comparable regulatory framework, Canadian organizations affected by supply chain outages must look to their own contracts to determine whether they are protected against an outage caused by a third party: specifically, whether the force majeure provision survives not only a pandemic but a widespread technology outage, and under what circumstances.

The sections below work through how force majeure provisions and service level agreements apply to outages, particularly in SaaS contracts.

Is an outage by a service provider a force majeure event?

The contract determines what counts as force majeure in most relationships, so the definition and its exclusions matter more than the label itself. Three drafting approaches are common:

  • A criteria-based definition (unforeseeable, irresistible, external), with no fixed list of events
  • An open list of illustrative events that meet those criteria
  • A closed list of events that will be treated as force majeure, and nothing else

A fourth approach, increasingly common in technology contracts, keeps the definition open but conditions it on preparation: force majeure is unavailable to a party that failed to maintain the business continuity measures the contract requires.

The same outage can come out differently depending only on which of these the contract uses. Take one fact pattern: a provider's critical function is down for six hours because its underlying cloud host suffers an infrastructure failure.

Closed list, silent on hosting

Lists only "natural disaster, war, act of government." No mention of hosting or sub-provider failures.

Not force majeureIf the clause is a closed list naming specific events and hosting isn't one of them, the outage is not force majeure under that contract, regardless of how unforeseeable or irresistible it actually was. The list controls.

Closed list, hosting included

Same list, plus "failure or unavailability of third-party hosting or cloud infrastructure."

Force majeureIf the same closed list expressly names failures of third-party hosting or cloud infrastructure, the identical outage is force majeure under that contract. Nothing else about the facts changed, only the drafting.

Open, criteria-based

"Any event beyond the party's reasonable control that it could not prevent through reasonable diligence." No named events.

Arguable either wayIf the clause is open and criteria-based, with no named events, the outcome is genuinely contestable, since the parties now have to argue about what "reasonable control" and "reasonable diligence" meant for this provider on this day. This is the weakest version for anyone who wants certainty going in.

Preparation-conditioned

Covers the event, but only if the party maintained the business continuity measures set out in the contract's own schedule.

Depends on the scheduleIf the clause is preparation-conditioned, the outcome turns on a fact the parties can establish in advance: did this provider maintain the redundancy, failover, and tested continuity plan the contract required of it? If yes, the clause covers the outage. If the provider ran single-region with no tested recovery plan despite having agreed to maintain one, the clause excludes it, not because a court weighed the equities, but because the provider didn't meet its own contract's precondition.

The drafting choice is the whole ballgame. A provider negotiating from strength will push for the closed list that excludes hosting failures, or the open criteria clause that leaves room to argue. A customer with real leverage, or real exposure if the service goes down, should push for the preparation-conditioned version, because it is the only one of the four that rewards the provider for actually being prepared rather than for how the clause happens to be worded.

For SaaS contracts in particular, the treatment of upstream provider failures deserves the same scrutiny. A supplier that depends on a cloud platform to deliver its service should decide with its customer, in the contract, whether an upstream failure falls inside or outside the force majeure clause, and tie that answer to continuity measures the supplier is actually required to maintain, rather than leaving it to whichever definition happens to be in the template.

What happens when a contract doesn't define force majeure?

A contract that is silent on force majeure, or that has no force majeure clause at all, doesn't leave the question unanswered. It just means the answer comes from something other than the parties' own drafting, and what fills that gap depends on the legal and regulatory framework governing the relationship.

Some systems address it through codified legislation. Quebec is one example, discussed below: Article 1470 C.C.Q. sets out a default rule for superior force even where the contract itself is silent. Other civil law systems follow a similar structure, France's force majeure under the Code civil among them.

Other frameworks address outage risk through sector-specific regulation rather than a general force majeure rule. DORA, discussed above, is one example: rather than asking after the fact whether an outage excuses non-performance, it requires financial institutions and their critical technology providers to prepare for disruption in advance, through oversight, testing, and continuity planning.

And in some legal systems, the gap is filled by narrower doctrines built up through case law rather than codified rules, such as the doctrine of frustration, which generally excuses performance only where a contract's purpose has been destroyed entirely, not merely made harder or more expensive.

Which of these applies, and how much protection it offers, depends entirely on the jurisdiction and regulatory framework governing the relationship. That is itself a reason not to leave a technology contract silent on the point.

Superior force under Quebec's Civil Code

In Quebec, even where a contract includes no force majeure provision, Article 1470 C.C.Q. describes superior force as an unforeseeable and irresistible event, including external causes with the same characteristics. A party that proves superior force may be released from liability for the resulting injury.

This rule is not mandatory. Parties may define superior force in their contract, broaden it, narrow it, or allocate the risk of certain events to one party regardless, and technology agreements usually do exactly that. Once they have, the contract, not the Code, becomes the primary reference when an outage occurs.

So why does a well-drafted provision matter even where the Code already supplies a failsafe? Because the general three-criteria test doesn't map cleanly onto a cloud outage, and leaving it to the Code means leaving it to a court's interpretation of facts the parties could have addressed themselves:

  • Foreseeability. Large platform outages are no longer rare events. One analysis counts this as Microsoft's third major Microsoft 365 outage of 2026, after incidents in January and September. When disruptions recur this often, arguing that one more was unforeseeable may be difficult.[4]
  • Externality. A provider that builds its service on a hyperscaler chose that dependency. An event within a party's own supply chain is not easily characterized as external to that party, unless the contract says otherwise.
  • Irresistibility. Even when an outage originates upstream, the analysis may turn on whether the affected party could have avoided or limited its consequences, through failover, redundancy or other measures within its control.

What counts as a breach of contract in case of unavailability?

A failure to meet the requirements of force majeure does not automatically mean a breach has occurred, or that a service provider is liable. Whether a breach occurred depends on how availability was promised, which is particularly relevant in SaaS contracts and cloud agreements.

Élodie Meyer, General Counsel at Ceiba Law
Clients often assume an outage that breaches the SLA is automatically a breach of contract, and the two are not the same question. The SLA tells you whether a service credit is owed. Whether the agreement itself has been breached, and what remedies follow from that, is a separate question answered elsewhere in the contract.
Élodie MeyerGeneral CounselPartnerCeiba Law

Most technology agreements express availability through a service level agreement (the "SLA"). A 99.9% monthly commitment allows roughly 43 minutes of downtime in a 30-day month (0.1% of 43,200 minutes). An outage close to a full day (1,440 minutes) brings monthly availability down to approximately 97% (41,760 ÷ 43,200 ≈ 96.7%), assuming all users are affected. Some providers, including Microsoft, measure downtime per affected user, so a partial outage yields a higher figure.[5] Availability may also be defined quantitatively, and this definition can vary from one contract to another. Finally, an SLA may define liquidated damages payable in advance for a breach (for example, cloud credits), often on terms making those credits the sole remedy.

SLA review checklist: questions to ask before you sign

  • Is availability measured per service, per region, or across the platform? Does degraded performance count?
  • Are there exclusions for scheduled maintenance, emergency maintenance, upstream provider failures, and superior force events?
  • Can emergency maintenance, including backlog patching, cause system disruption, and under what circumstances?
  • Are service credits the sole remedy? Is a single breach enough to trigger material breach of the contract?

For SaaS providers, understanding the SLA and continuity requirements that critical infrastructure customers impose, and extending equivalent commitments to their own subcontractors, is a business continuity question as much as a drafting one. Few standard supplier agreements are built to pass critical-infrastructure-level requirements downstream without creating a liability gap.

Customers running high-availability systems, such as critical infrastructure operators, generally need more than a standard SLA: providers offering redundancy across environments, enhanced SLA terms, and an integrated business continuity strategy become necessary.

Beyond the boilerplate

A force majeure clause is only one line in a much longer story about how a relationship absorbs disruption. The contract writes the rules for how the parties deal with each other when something goes wrong; it doesn't replace the technical controls that determine whether something goes wrong in the first place, including the availability measures a supplier actually runs, and, where the nature of the service calls for it, the data residency and sovereignty commitments layered on top. Read the clause in isolation and it's easy to come away with a misleading sense of where the real risk sits.

Three things worth carrying forward:

  • Read the clause in context, not isolation. A force majeure provision only means what it says once you've checked it against the SLA, the liability cap, the security schedule, and the business continuity commitments sitting next to it. Each of those can quietly expand or narrow what the clause actually does.
  • A contract is not a continuity plan. If a supplier is critical to operations, the right to a remedy after the fact does not keep those operations running during the outage. Preparation, not paperwork, is what gets a business through the six hours.
  • The right allocation depends on the relationship, not the template. A standard SaaS agreement spreads risk across every tenant on the platform, and a supplier has to be able to keep operating within that model. A customer running a critical function on top of it still needs real assurances. Getting that balance right takes judgment, not a boilerplate clause copied from the last deal.
Vanessa Henri, Managing Partner at Ceiba Law
A force majeure clause tells you who absorbs the cost once the outage is over. It does not shorten the outage, and it is not a substitute for a continuity plan. The clause only does the work you drafted it to do. The redundancy, the failover, the tested recovery plan, all of that has to exist before the outage. It cannot be argued into existence after it.
Vanessa HenriManaging PartnerCeiba Law

November's string of outages won't be the last. The organizations best positioned for the next one will have reviewed these provisions in advance, rather than reading the force majeure clause for the first time while the outage clock is running.

Ceiba Law advises organizations on technology procurement and SaaS contracts and incident response, including how force majeure, availability, and continuity obligations are allocated across supplier and customer agreements. For related considerations on supplier dependency, see our digital sovereignty article and our php2shell post-mortem.

Sources

  1. NBC News, Microsoft outage live blog: Outlook and Teams updates, November 2026. https://www.nbcnews.com/tech/tech-news/live-blog/microsoft-outage-outlook-teams-updates-fix-rcna609118
  2. Federal Aviation Administration, Air Traffic Control System Command Center, ground stop advisory, November 13, 2026. https://www.fly.faa.gov/ois/oisedit/adv_oisedit_dis?day=11132026&gstop=196093&number=111
  3. European Union, Regulation (EU) 2022/2554 on digital operational resilience for the financial sector (DORA), Articles 11 and 28–31. https://eur-lex.europa.eu/eli/reg/2022/2554/oj/eng
  4. Windows Forum, November 2026 outages: Microsoft 365 gateway bug, Apple update and unproven cyberattack claims. https://windowsforum.com/news/november-2026-outages-microsoft-365-gateway-bug-apple-update-and-unproven-cyberattack-claims.452850/
  5. Microsoft, Service Level Agreements (SLA) for Online Services, Monthly Uptime Percentage. https://www.microsoft.com/licensing/docs/view/Service-Level-Agreements-SLA-for-Online-Services

Related solutions

  • Breach Coach

    When a breach is suspected, the decisions made in the first hours shape everything that follows. As your breach coach, we structure the response to preserve privilege, coordinate forensic, insurance and communications partners, assess notification obligations to regulators and individuals, and guide investigations, including insider threats, through to closure.

    View solution
  • Fractional General Counsel

    Our fractional general counsel service supports technology businesses and existing legal teams with ongoing advice, contract negotiations and legal operations. We work with your leadership, sales and technical teams to address current matters and establish useful templates, processes and automations.

    View solution
  • Tech RFP Management

    We turn procurement into a strategic advantage. Our interdisciplinary team structures and runs technology tenders end to end, combining legal and cybersecurity expertise to define requirements, assess vendors and negotiate contracts.

    View solution

Related expertise

  • Technology Procurement

    Technology contracts lawyers for SaaS, cloud, software, AI and managed services agreements with clear data, security and exit terms.

    View expertise
  • Corporate Law

    Corporate law for technology companies: structure, governance and commercial agreements that support your growth in Canada.

    View expertise
  • Incident Response

    Cyber incident response led by legal counsel, coordinating forensic specialists and partners through containment, recovery and follow-up.

    View expertise
  • Cybersecurity

    Cybersecurity law advice linking security governance, contractual commitments and legal obligations to how you manage cyber risk.

    View expertise

Your advisors

Ceiba Law relies on a team of experts who specialize in their respective fields to provide you with the best advice.

Contact us

Insights